FAQ

  1. Design FAQ
  2. Easement FAQ
  3. Construction FAQ

1.   How long is the design phase?

The design phase for a stream restoration project is typically two (2) years.

2.   What is the first step of the design phase?

Collection of field data including wetland and tree identification and stream channel measurements.

3.  What permits are needed?

  • Harford County - grading permit
  • Harford County - stormwater management waiver
  • Maryland Department of Environment - wetlands and waterways permit
  • Maryland Department of Environment - general permit for stormwater associated with construction activity
  • U.S. Army Corps of Engineers - permit authorization

4.  Will the design be available for review?

Yes, the design will be available for review, digitally on this webpage or printed copies will be available in our offices at 212 South Bond Street.  Each submittal from the design engineer will be available for review.  Property owners will be notified by email, phone, or mail when the plans are available.